Back in 2023, in the final months of the previous NSW Government, an ambitious plan was published to deliver a connected network of high-quality cycleways.
The Strategic Cycleway Corridors program set out the blueprint for 1,000 kilometres of safe and accessible cycleways across Greater Metropolitan Sydney, the Illawarra-Shoalhaven, Lower Hunter and Greater Newcastle.
The Strategic Cycleways Corridors map for Greater Sydney, published in February 2023 (Source: Transport for NSW)
As discussed in our recent article What is the Principal Bike Network?, the Strategic Cycleway Corridors (SCC) program superseded the Principal Bicycle Network (PBN), which had been quietly shelved by the NSW Government in 2020.
The SCC program was intended to be more streamlined and practical. It avoided committing to alignments. Transport for NSW wanted more flexibility so that projects could evolve in response to the latest information regarding housing density, employment centres, points of interest, and transport infrastructure.
Bicycle NSW wrote a helpful explainer on the Strategic Cycleway Corridors in 2023.
What has happened since 2023?
Over two years and many workshops, Bicycle NSW and the Bicycle User Groups provided feedback and recommendations for project alignment and priorities.
In each meeting, the list of potential projects that Transport for NSW planned to deliver under a Tranche 1 business case was whittled down. By the time of the last workshop in March 2025, there were just 14 connections on the list across Greater Sydney, Newcastle, the Illawarra and the Central Coast.
None of these cycleways have been built yet.
The clock is ticking. In December 2022, the very first NSW Active Transport Strategy committed to partner with councils to construct 100 kilometres of new, connected strategic cycleways by 2028. The subsequent Connecting NSW Strategy watered down this target but still promised a steady increase in kilometres of cycleways and shared paths.
Despite the glacial progress on the standalone Tranche 1 projects, Bicycle NSW is aware that, actually, several chunks of new cycling infrastructure that contribute to SCCs have been delivered - either by councils using Get NSW Active funding, or through major road and rail projects under the positive provisioning Providing for Walking and Cycling in Transport Projects Policy.
The fantastic separated walking and cycling paths through Bayside's Scarborough Park, built by the M6 Motorway and opened in December 2025 (Image: Bicycle NSW)
Why we need an update now
The current status of the SCC program is important for Changing Gears, the strategic advocacy plan that Bicycle NSW is developing to inspire politicians to accelerate investment in active transport infrastructure. We want to tailor our recommendations to build on existing NSW Government planning work on cycleways.
So we asked the Active Transport team at Transport for NSW for the following:
- A digital network map showing completed and future strategic cycleways, with accurate alignments where known
- An update on the Tranche 1 projects and the business case
- A breakdown of SCC-aligned projects that have been delivered by Transport for NSW and councils
- A list of SCC-aligned projects that are funded and waiting in the pipeline
And this is what we learnt:
The Strategic Cycleway Corridors network map has not evolved
This is the most disappointing finding.
As part of the Changing Gears project, Bicycle NSW has commissioned a new model to identify the places where building infrastructure will deliver the best results. The model will reveal the cycleway corridors, missing links, rail trails and local connections that should be prioritised.
We need a strategic bike network map to feed into the model. Transport for NSW was unable to locate the 2020 digital version of the PBN, but assured us that the SCC shapefiles would contain the information we needed.
However, when we opened the shapefiles, we saw that the green lines from 2023 had simply turned red. No new information had been mapped.
The 2026 map does not show accurate routes for any of the SCCs, even where the alignment is known. Neither does it distinguish between what is delivered and what is proposed (Image: Transport for NSW)
Bicycle NSW has therefore had to divert scarce resources into recreating the map from scratch using outdated paper versions of the PBN.
As the lead bicycle advocacy group in NSW, we know it is critical to preserve possible corridors and provide clear guidance on route alignments for the many stakeholders involved with developing key cycleways. Our work will contribute to NSW Government policies and strategies that prioritise bicycle riding as a mode of transport.
Bicycle NSW will publish its digital network map very soon.
Six Tranche 1 projects are progressing
Six initial SCCs were selected from the shortlists discussed with BUGs between 2023 and 2025. The business case for these standalone Tranche 1 connections has been finalised.
We think the six projects are:
- Broadmeadow to Adamstown (City of Newcastle) 3.2km
- Gosford to Wyoming (Central Coast Council) 3.5km
- Penrith to South Penrith (Penrith City Council) 2.9km
- Coniston to Figtree (City of Wollongong) 2.9km
- Newtown to Green Square (City of Sydney) 2.3km
- Strathfield to Homebush (Strathfield Council) 1.0km
The first four corridors were part of an open EOI for technical advisory services advertised in June 2026. Transport for NSW’s chosen consultants are now developing the designs in collaboration with councils. Design work on the Newtown to Green Square project is being led by City of Sydney. Concept designs for the Strathfield to Homebush connection have already been completed by Strathfield Council.
The Active Transport team will soon be able to share further information with the community.
44.2 km of SCC links have been delivered since 2023
33.5 km of these kilometres have been delivered through major Transport for NSW projects:
Three very high-quality cycleways have done the heavy lifting in this list – the M12 Emu Trail from the M7 Cycleway to the Northern Road via the new Western Sydney International airport, the Parramatta Light Rail ATL from Parramatta to Carlingford, and the M6 Active Transport Corridor from Kyeemagh to Monterey.
Another 10.7 km of SCC links have been delivered in partnership with councils through the Get NSW Active Program:
60.9 km of links aligned with SCCs are funded for construction
This figure includes 48.5 km of cycleways that will be delivered by Transport for NSW through major projects or Transport-led infrastructure programs:
And a further 12.4 km of SCC links have been awarded construction funding through the Get NSW Active Program:
Note that there may be some errors in these tables.
This is the first time that Transport for NSW has attempted to report on the SCC program. Accuracy will improve as the audit process is refined.
Bicycle NSW recognises that it has been a lot of work to assemble the projects, and we thank the Active Transport team members for their efforts. Hopefully the lists are as useful for Transport for NSW as they are for advocates!
A more significant concern with Transport for NSW’s accounting
Several of the listed projects do not provide additional connectivity.
They involve renewing, rebuilding or widening existing paths or bridges, such as the Cooks River Shared Path Bridge.
Other projects replace perfectly good connections broken by major road or rail upgrades. The Jesmond Active Transport Bridge is an example.
We don't think these links should contribute to the target of ‘100km by 2028’.
It should also be highlighted that many of the listed projects were well underway when the SCC program was announced and the ‘100km by 2028’ target set.
They are not a direct result of the NSW Government’s work since 2023 to build a connected network of strategic cycleways.
And there is another major issue.
The majority of the 105.2 km delivered and funded kilometers in the tables are shared paths. Only 11.9 km are separated bicycle paths. This contravenes Transport for NSW's guidance in its very own Cycleway Design Toolbox that a shared path is not a suitable cycleway facility for priority routes.
What is needed to turbo-charge the SCC program?
Funding remains the critical issue.
The Get NSW Active grants have prioritised design funding over the last few years and capped construction funding at $5 million per council.
Where project have won funding, it is often a fraction of the total required. Look carefully at the table above and you will see that the funded Stage 1 section of the 2.2km Kingsford to South Coogee Cycleway via Sturt and Bundock streets is only 50m long!
There are millions of dollars of shovel-ready projects with no pathway for delivery.
“The Get NSW Active grants are incredible,” says Bicycle NSW CEO Peter McLean. “However, the program does too much heavy lifting which it wasn’t designed to do. And it can’t do, with only $60 million available each year.
“A key recommendation in the Changing Gears plan will be to continue Get NSW Active, but add a separate grant program, starting at $60 million and ramping up each year, that focuses on the construction of the many fully-designed strategic cycleways.”
Keen to support Bicycle NSW's work on Changing Gears?
Then please become a Bicycle NSW Member!
Bicycle NSW has campaigned for a better environment for bike riding for 50 years. It is the only bicycle advocacy group based in NSW with full-time staff advocating every day for all riders.
Each year we write more than 60 submissions and letters to councils, ministers, government bodies and Transport for NSW. This is more than all the other state peak bodies combined!
Bicycle NSW Members fund our vital advocacy efforts, but they also enjoy the peace of mind that comes with our comprehensive insurance and exclusive Member-only perks.
If you are not ready to join the Bicycle NSW family, then we would love you to consider a donation to the Australian Bicycle Advocacy Fund.